Overvoltage Selection & Coordination
From surge sources and waveforms to a decision logic across SPD/MOV/TMOV/GDT/TVS/ESD, plus energy coordination and the Up cascade rule for multi-stage protection.
Overvoltage sources
Lightning, switching, device start/stop; 1.2/50, 8/20 waveforms and energy levels.
To textDevice roles
GDT / MOV / TVS / ESD each cover a range, matched by location and current.
To textSelection decision tree
Back-calculate protection class and In rating from where equipment sits.
ViewThree coordination rules
Time gap, energy gap, voltage gap; avoid undersized upstream or damaged downstream.
To textParameter checklist
Uc, In/Imax, Up, response time, residual margin, backup fuse.
ViewWhere Overvoltage Comes From
Good selection starts with knowing the enemy. Overvoltage on a circuit falls into four classes:
| Source | Typical waveform | Magnitude | Example |
|---|---|---|---|
| Lightning induction/strike | 10/350 µs, 8/20 µs | kA currents | service entrance, rooftop gear |
| Switching overvoltage | slow front, oscillatory | several kV | switching large loads, inductive |
| ESD | human body 150 pF / 330 Ω | ±15 kV contact | human touches a port |
| Transient surge (coupled) | 10/1000 µs, combination wave | hundreds V–kV | inductive loads, long-line coupling |
The waveform decides which device: high energy/current → GDT/MOV; fast and precise → TVS/ESD.
Device Division of Labor
| Device | Response | Current/energy | Residual | Best at |
|---|---|---|---|---|
| GDT | µs | huge (kA–tens kA) | mid | stage 1 / comms |
| MOV | ~25 ns | large | mid-low | stage 2 / power |
| TMOV | ~25 ns | large | mid-low | safe mains MOV |
| TVS | ps | mid | very low | stage 3 / signal & power |
| ESD | ps | small | very low | interface static |
Note
There is no "universal device." GDT has huge current but high residual and slow response; TVS is fast and precise but cannot absorb large energy. Only coordination covers both.
Selection Decision Tree
What interface is being protected?
├─ AC/DC power entry (high energy)
│ ├─ main distribution → Type 1/1+2 SPD (MOV+GDT, Iimp/In by lightning zone)
│ ├─ sub-distribution → Type 2 SPD
│ └─ in-equipment → Type 3 + board-level TVS
├─ comms/signal line (low capacitance)
│ ├─ external/primary → GDT (or GDT+MOV)
│ └─ board interface → TVS / ESD array
└─ high-speed data (USB/Ethernet/HDMI)
└─ ultra-low-cap ESD array (<0.5 pF)
Three Coordination Principles
- Energy coordination (decoupling): the upstream stage absorbs most energy; the downstream only handles the remainder. A decoupling element (inductor/resistor/lead inductance) between stages lets the upstream act first. Without decoupling the downstream fires first and gets destroyed.
- Up cascade: the upstream Up (residual) should be ≤ the downstream Up. E.g. SPD residual 1.2 kV, equipment TVS residual 30 V—decoupling grades the energy between them.
- Decreasing thresholds: from line to ground, each stage's breakdown/action voltage should step down, forming a "graded diversion."
Key reminder
The classic symptom of failed coordination: the equipment-side TVS burns out repeatedly while the upstream SPD is fine. Root cause is insufficient decoupling—energy wasn't eaten by the upstream. Follow the vendor coordination table or add decoupling.
Parameter Checklist
- [ ] max line operating voltage → Uc / Vwm
- [ ] equipment withstand Uw → Up / Vc (20% margin)
- [ ] expected surge level → In / Imax / Ipp / Ppp
- [ ] install position → Type 1/2/3 and device mix
- [ ] inter-stage decoupling → inductor/resistor/lead length
- [ ] mains MOV → use TMOV (fire safety)
- [ ] SPD front end → SCPD backup
Next
- Device library: SPD · MOV · TMOV · GDT · TVS · ESD
- Read Overcurrent selection and Thermal & inrush protection
Where Overvoltage Comes From
Good selection starts with knowing the enemy. Overvoltage on a circuit falls into four classes:
| Source | Typical waveform | Magnitude | Example |
|---|---|---|---|
| Lightning induction/strike | 10/350 µs, 8/20 µs | kA currents | service entrance, rooftop gear |
| Switching overvoltage | slow front, oscillatory | several kV | switching large loads, inductive |
| ESD | human body 150 pF / 330 Ω | ±15 kV contact | human touches a port |
| Transient surge (coupled) | 10/1000 µs, combination wave | hundreds V–kV | inductive loads, long-line coupling |
The waveform decides which device: high energy/current → GDT/MOV; fast and precise → TVS/ESD.
Device Division of Labor
| Device | Response | Current/energy | Residual | Best at |
|---|---|---|---|---|
| GDT | µs | huge (kA–tens kA) | mid | stage 1 / comms |
| MOV | ~25 ns | large | mid-low | stage 2 / power |
| TMOV | ~25 ns | large | mid-low | safe mains MOV |
| TVS | ps | mid | very low | stage 3 / signal & power |
| ESD | ps | small | very low | interface static |
Note
There is no "universal device." GDT has huge current but high residual and slow response; TVS is fast and precise but cannot absorb large energy. Only coordination covers both.
Selection Decision Tree
What interface is being protected?
├─ AC/DC power entry (high energy)
│ ├─ main distribution → Type 1/1+2 SPD (MOV+GDT, Iimp/In by lightning zone)
│ ├─ sub-distribution → Type 2 SPD
│ └─ in-equipment → Type 3 + board-level TVS
├─ comms/signal line (low capacitance)
│ ├─ external/primary → GDT (or GDT+MOV)
│ └─ board interface → TVS / ESD array
└─ high-speed data (USB/Ethernet/HDMI)
└─ ultra-low-cap ESD array (<0.5 pF)
Three Coordination Principles
- Energy coordination (decoupling): the upstream stage absorbs most energy; the downstream only handles the remainder. A decoupling element (inductor/resistor/lead inductance) between stages lets the upstream act first. Without decoupling the downstream fires first and gets destroyed.
- Up cascade: the upstream Up (residual) should be ≤ the downstream Up. E.g. SPD residual 1.2 kV, equipment TVS residual 30 V—decoupling grades the energy between them.
- Decreasing thresholds: from line to ground, each stage's breakdown/action voltage should step down, forming a "graded diversion."
Key reminder
The classic symptom of failed coordination: the equipment-side TVS burns out repeatedly while the upstream SPD is fine. Root cause is insufficient decoupling—energy wasn't eaten by the upstream. Follow the vendor coordination table or add decoupling.
Parameter Checklist
- [ ] max line operating voltage → Uc / Vwm
- [ ] equipment withstand Uw → Up / Vc (20% margin)
- [ ] expected surge level → In / Imax / Ipp / Ppp
- [ ] install position → Type 1/2/3 and device mix
- [ ] inter-stage decoupling → inductor/resistor/lead length
- [ ] mains MOV → use TMOV (fire safety)
- [ ] SPD front end → SCPD backup
Next
- Device library: SPD · MOV · TMOV · GDT · TVS · ESD
- Read Overcurrent selection and Thermal & inrush protection